June project update

Work on the King Island Renewable Energy Integration Project (KIREIP) is coming along well. The power station building extensions are now almost finished, allowing some of the new element of the power system to be installed. The Uninterruptible Power Supply class Diesel engines (D-UPS) have arrived on King Island and have been moved into their ‘bays’ ready to be connected. Bio Diesel trials are continuing, the current trial is using a mix of 20% Bio Diesel with traditional Mineral Diesel.